Utility-scale solar and solar farm EPC in Texas
Texas has land, a large grid, and fast-growing load, which is why it leads the country in new utility-scale solar and storage. As a solar farm EPC contractor, our role is delivering a bankable project: geotechnical and hydrology work, pile and tracker design, collection system and substation engineering, and a construction schedule that lenders and tax equity can underwrite. The standards we apply are described in what makes a solar farm EPC bankable.
Interconnection: ERCOT GINR
Larger generation and storage projects connecting to the ERCOT transmission system go through ERCOT's Generation Interconnection or Change Request (GINR) process, with studies performed by ERCOT and the interconnecting transmission service provider. Smaller distribution-connected resources follow the TDU's distributed generation process. The GINR queue is large, and study results drive both schedule and network upgrade cost, so we engage on interconnection early in development rather than after design is complete.
Offtake and PPAs
Because merchant midday prices are weak, most Texas utility-scale projects are financed on a power purchase agreement, virtual PPA, or hedge with a corporate buyer or utility. Contract settlement point, shape (fixed-shape vs. as-generated), and basis risk between the project node and the hub all feed the EPC design, for example in the choice between fixed tilt and single-axis tracking, and the size of co-located storage.
Landowners and developers
If you own land and are evaluating a lease, see our guide to leasing land for a solar farm. If you are developing a project, our solar farm development guide lays out the sequence from site control to notice to proceed.
2025 legislative session
During the 2025 session the Texas Senate passed several bills that would have constrained renewable development, including SB 819 (added permitting and fees for wind and solar), SB 388 (dispatchable generation requirements), and SB 715 (backup requirements for renewables). None of these passed the House. A bill on end-of-life handling of solar and wind equipment did advance. Legislative risk remains a diligence item for Texas projects; confirm current law with counsel.