In Massachusetts, the utility interconnection process often takes longer than building the solar system. For a commercial owner facing a federal placed-in-service deadline, it is the part of the schedule that deserves the most attention and gets the least.
Commercial solar in Massachusetts interconnects under each utility's DPU-approved Standards for Interconnection of Distributed Generation tariff, through one of three paths: Simplified (inverter systems of 25 kW or less on lightly loaded circuits, 25 business days maximum), Expedited (systems that pass the utility's screens, 45 to 65 business days), or Standard (everything else, 135 business days or more, with 200 or more for complex projects). Projects in a congested area may be pulled into a group study, and in some areas pay a per-kW Capital Investment Project fee. Timelines stop whenever the utility is waiting on the customer, and utility construction comes after all of this.
The rules: one model tariff, three utilities
Interconnection of distributed generation in Massachusetts is regulated by the Department of Public Utilities. Each investor-owned distribution company files its own Standards for Interconnection of Distributed Generation tariff, built from a common model tariff the DPU oversees. The three companies are NSTAR Electric d/b/a Eversource Energy, Massachusetts Electric d/b/a National Grid, and Fitchburg Gas and Electric Light d/b/a Unitil. Municipal light plants set their own rules and are outside this guide.
Before a system operates in parallel with the grid, the owner must have an executed Interconnection Service Agreement and a written Authorization to Connect from the utility. Every new generating source, regardless of ownership or technology, has to apply and pay the applicable fee.
The tariff changed in 2026. The Interconnection Implementation Review Group, a stakeholder body established by the DPU, filed proposed revisions in March 2025, and the DPU opened D.P.U. 25-48 to review them. According to the Commonwealth's interconnection page, the DPU approved revised interconnection tariffs for all three utilities in April 2026. Eversource's current tariff, M.D.P.U. No. 55G, took effect August 20, 2026. The figures in this guide are taken from that tariff; National Grid and Unitil tariffs follow the same model but should be checked directly.
Simplified, Expedited, and Standard
The tariff defines three paths. Which one a project takes depends on size, equipment, the type of distribution circuit, and whether it passes a series of technical screens.
Simplified
For listed inverter-based facilities of 25 kW or less on single-phase or three-phase secondary service, on a radial circuit where aggregate generation is less than 15 percent of the feeder's annual peak load. Raising this threshold from 15 kW to 25 kW was one of the consensus changes in D.P.U. 25-48. Few commercial systems fit here, but small carports and pilot installations can.
Expedited
For listed facilities on radial circuits that pass the utility's initial screens. The utility runs the full screening methodology and may do internal studies at no extra charge. If the project fails a screen, it goes to Supplemental Review or to the Standard Process. Even a project that passes every screen can still require minor system modifications, which are identified and priced in the Interconnection Service Agreement.
Standard
For everything that does not qualify for Simplified or Expedited, and for all facilities on area network systems, which are common in dense downtown areas. The Standard Process includes an initial review and, where needed, an impact study and a detailed study, paid at actual cost. Owners who know their project will not pass Expedited screens can go straight to Standard.
Pre-Application Report. Any facility of 250 kW or more must request and receive a Pre-Application Report before filing an Expedited or Standard application. Smaller projects may request one. It is the cheapest early look at what the circuit can take, and it should be done before design is frozen.